Introduction
The PERT is a project management tool that provides a more accurate way of estimating the time it will take to complete a project. It does this by giving 3 types of estimates: your most optimistic, most likely, and most pessimistic estimates in the hours you think it will take to complete each task. This provides a new, as well as a risk factor associated with each task.
On the left side of the page is the proposal structure. You can select an item from this list by clicking the tickbox to its left. This allows you to record estimates for all labour performed on the project level and within each sub-assembly.
Detail
General
Field | Description | Notes |
---|---|---|
Pre Proposal (PERT Active) | Marks this proposal as a pre-proposal | While this is ticked, updates to the PERT Estimation Tool will be carried over to the proposal. |
Is Internal | Marks this an internal proposal | This should only be ticked for proposals for your own company. These proposals/projects will not be displayed in WIP or revenue-based reports. |
Requires BOM | Marks that this proposal will require a Bill of Materials | |
Proposal Status | The current status of the proposal. | Defaults to "New" |
Project Group | The project group this proposal is a part of | |
Proposal Number | A number that uniquely identifies this proposal | This number is automatically generated by Integro and cannot be edited |
Project Type | The type of this project | Project types can be set up in the Settings Section. |
Title | The title of the proposal | |
Customer | The customer this PERT is for | To add a new customer, see Add a New Customer |
Customer Contact | The customer contact for this proposal | If no customer contact currently exists, a + button on this field allows you to add a new customer contact. |
Key Dates
Field | Description | Notes |
---|---|---|
Enquiry Received Date | The date of the initial request from the customer for this proposal | |
Proposal Due Date | The due date for when this proposal is to be completed and sent to the customer. | |
Proposal Sent Date | The date this proposal was last emailed to the customer. | |
Customer Delivery Date | The due date for the finished project |
Key Personnel
Field | Description | Notes |
---|---|---|
Proposal Owner | The employee responsible for overseeing this proposal | |
Contact | The employee responsible for overseeing the listed process | |
PERT Completed | Employee name and date the PERT for the listed process was completed. | |
PERT Approved | Employee name and date the PERT for the listed process was approved. |
Labour
The labour tab will show all labour for the selected item in the proposal structure tree. The labour grid consists of three main levels. The top level, represented by a dark blue colour, is the project process. The second level, represented by a lighter blue colour, is the proposal process. The third level and below are pert tasks. Each allows you to log your optimistic, likely, and pessimistic estimates for the labour. From this, we generate Pert Risk as well as Estimated Hours.
Field | Description | Notes |
---|---|---|
Activity | Name of the project process, proposal process or task | |
Optimistic | The most optimistic time in hours it will take to complete this labour. | |
Most Likely | The most likely time in hours it will take to complete this labour. | |
Pessimistic | The most pessimistic time in hours it will take to complete this labour. | |
PERT Risk | Risk-based on the uncertainty | |
Risk Hours | The difference between Pessimistic and Most Likely | |
Est. Hrs | Estimated hours it will take to complete this labour | This field is calculated based on optimistic, most likely and pessimistic |
Est. Days | Estimated hours formatted as days | |
Notes | Additional notes | |
Internal Assumptions | Assumptions that are only visible internally | |
Employee Level | The level of experience of employees performing this labour |
Summary
This grid summarises PERT hours from the selected proposal structure item and its children. It contains the same columns as the Labour grid, but they are grouped and totalled by the following: Process group, Process, Proposal Root, Module, Station.
These are the only additional columns from the Labour grid:
Field | Description | Notes |
---|---|---|
Module Qty | Number of duplicate Modules this record is in | This defaults to 1 if it does not belong to any module |
Station Qty | Number of duplicate Stations this record is in | This defaults to 1 if it does not belong to any station |
Assumptions
This grid lists any assumptions that are made for this proposal.
Field | Description | Notes |
---|---|---|
Name | Name of the assumption | |
Owner | The employee responsible for this assumption | |
Validator | The employee who has validated this assumption | |
Project Phase | The project phase this assumption effects |
Was this article helpful?
That’s Great!
Thank you for your feedback
Sorry! We couldn't be helpful
Thank you for your feedback
Feedback sent
We appreciate your effort and will try to fix the article