Overview

Use this information when designing the bill of materials template for Solidworks Mechanical. The information on this page is subject to change to align with requirements.

  • The order in which the columns appear is critical.
  • The first 11 fields (highlighted) are compulsory.
  • If you want to include a higher number column, you must include all previous columns (they may be left blank if you wish)
  • The field name is suggested but you may modify this, however, the function of the field cannot be changed.

Import File Specification

PositionField NameTypeExampleDescription
1Item No.String1.3.12A hierarchical number describing the location of the part
2Part NumberStringPT1234-534The internal or manufacturer’s part number
3QuantityInteger12
4DescriptionString(500)FG22-LG43-GR5Description or configuration of part
5VersionStringRev1Version or revision
6Supplier Part NumberStringSup-PT1234-534The part number assigned to this part by the supplier is named below
7SupplierStringSMCThe name of the supplier sourced by the designer - These need to be configured in the Setting Screen
8ManufacturerStringSiemensThe manufacturer of the part - These need to be configured in the Settings Screen
9SparesStringY or YesIs this a spare part
10IllustrativeStringY or YesIgnore this part, i.e. it is on the model but should not be included on the BOM
11TypeStringSee Description

E.G.

A = Assemblies,
C = Custom Tooling Parts or Laser Cut,
H = Machined Parts,
P = Purchased Part,
M = Modified Purchased Part,
R = Reference Only (same as Illustrative)

- These need to be configured in the Settings Screen

12MaterialStringMild Steel
13FinishStringPOWDER COATED, RAL 7035 GREYThe finish to be applied to the part
14Material Part NumberstringS1The spare part level or criticality - These need to be configured in the Setting Screen
15Spare Levelstringe.g. Critical, 1, 2, etc.A value from the predefined Spare Levels in Integro.
16OnHoldStringY or YesEven though this part is on the BOM, it should not yet be purchased
17Is Conformance Cert RequiredStringY or YesYes, if a Conformance Certificate is required for this part.
18Is Dimensional Cert RequiredStringY or YesYes, if a Dimensional Certificate is required for this part.
19Massdecimal100The mass of the part in grammes
20Drawn ByStringMartin McSharryThe name of the person who created the part
21NotesStringLong lead itemAre there any extra notes about the part? This does not constitute part of the specification
22Total Bounding Box Lengthdecimal100.25The length of the “best fit” bounding box feature of the 3D model.
23Total Bounding Box Widthdecimal50.12The width of the “best fit” bounding box feature of the 3D model.
24Total Bounding Box ThicknessdecimalThe height of the “best fit” bounding box feature of the 3D model.
25Bounding Box Lengthdecimal122.05The length of the flat pattern feature of the 3D model.
26Bounding Box WidthdecimalThe width of the flat pattern feature of the 3D model.
27Sheet Metal Thicknessdecimal
28Cut LengthdecimalThe cut length of a cut-list item.

Import Process

The process checks to see if a part has already been imported. It does this by comparing the following items:

  • Part Number
  • Category
  • Manufacturer
  • Revision

Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select at least one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article