How to: Transfer Stock to Project

Modified on Sat, 13 Jul, 2024 at 6:01 PM

Overview

Integro allows you to transfer stock to a project, i.e. allocate parts to the project even though they were not originally purchased for that project.  Parts that have been transferred to a project are automatically removed from stock.


Only use this method if the stock you want to add to the project is not on the BoM.  Otherwise, use the [Transfer From Stock] method on the BoM itself.


Step-by-Step Guide

Goto [Inventory] - [All Master Parts].


  • Select the part(s) you want to add to the project.
  • Click the [Transfer To Project] button.
  • Select the project to which you want to transfer the part(s).
  • When the [Transfer to Project] popup is displayed, enter the number of parts you want to transfer to the project in the [Units to Transfer] column.

     

Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select at least one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article